Tianjing Zhongwang conducted a fire test onits cold rolling mill plant on 14th April. The test was undergone smoothly and the cold rolling mill has been proven safe for the coming equipment tests.
Currently the installation work of the 2350mm cold rolling mill was basically completed and went through the trial test in early April. The test of the CO2 extinguishing system was conducted on 14th April as scheduled.
The CO2 extinguishing system was designed, produced and installed by China Nonferrous Metals Processing Technology Co.,Ltd. The system is large in capacity whilesmall in size. It is also highly automotive, safe and efficient.